24直播网 11月19日讯 每日体育报》揭露,诺坎普工地建设稳步前进,利马克公司约3000名工人奋战在工地内外,新工期安排已确定。尽管下周日巴萨将迎来重返诺坎普周年纪念,工程进度未受影响,投资方及经济部门压力依旧不减。
《每日体育报》西班牙媒体报道,11月19日传来最新消息,诺坎普球场建设项目进展顺利,目前约3000名利马克公司工作人员正在球场及其周边区域忙碌施工。新的开放里程碑已经确定。
在即将到来的11月22日,巴萨将迎来重返诺坎普球场的一周年纪念日。尽管如此,工程团队并未放缓脚步,投资者和财政部门施加的压力依然显著。球场内部及周边的施工工作仍在高效进行中,这一切都得益于巴萨运营总监森特列斯的精心协调。
The initial structure to be unveiled is the new museum, scheduled for its grand opening in December, situated on the second level of the主席台side grandstand, boasting a sprawling area of 2500 square meters. In the first quarter of 2027, the new official store and Barça Café are set to welcome visitors. March will mark the inaugural use of the side grandstand's circular VIP lounge area, a decision reached in collaboration with Goldman Sachs and Limac, with the aim of securing revenue from this section before the season concludes being deemed a top priority. Following the end of the current season, Frick's squad will play a few matches at the Montjuïc Olympic Stadium before the Nou Camp Stadium commences the installation of its roof. Post the opening of the side grandstand VIP lounges, the stadium's capacity is poised to swell to approximately 66,000 spectators.
在诺坎普,即将启动顶棚的安装和张拉工程,这一过程预计耗时介于15至20天。然而,球队重返球场的时间依旧遥遥无期。尚有许多任务待完成,包括对草皮的更换、约18000个座椅的移除以方便施工进行,以及顶棚电缆的重新布局,确保其能顺利穿越指定区域。
预计工程将在2027年11月竣工,然而,许可证的获取情况则有所不同。巴塞罗那足球俱乐部已与该市市政当局签署了一项协议,确保下一赛季能够全面利用蒙锥克体育场。俱乐部渴望提前重返诺坎普球场,预计届时球场将容纳大约7万名观众。为了实现这一目标,俱乐部需获得使用二层看台最后几排的许可,并确保新闻区和UCO区域在三层看台开放。在完成顶棚的吊装后,将进行膜材的铺设,整个工程预计耗时约6个月。尽管足球赛事回归时顶棚尚未完全封闭,但最终完工后的顶棚重量将达到约6200吨,并在球门区域延伸至禁区内,从而在雨天保护守门员免受雨水侵袭。
尽管目前三层看台尚未对外开放,但安装座椅的工作已全面启动。预计在下一赛季,这些看台将正式投入使用,届时容纳人数将突破10.4万大关。为了实现从7万到超过10.4万的增长,三层看台以及主席台两侧和球门后的VIP包厢将一并开放。相关区域的许可证已经发放,而从已安装的座椅中可以看出,侧面看台将镶嵌有巴塞罗那队的标志,而主席台一侧将展示“不仅仅是一家俱乐部”的口号。
In the 2027-2028 season, as the team returns to the iconic Nou Camp stadium, a comprehensive deployment of ten vertical circulation hubs is scheduled. Each hub will be equipped with six elevators, tallying over ninety units throughout the venue. In stark contrast, the old stadium boasted merely four elevators. Additionally, the Nou Camp will be fitted with a substantial number of escalators.
In the 2028-2029 season, which coincides with the UEFA Champions League final being held at the Nou Camp, the stadium is undergoing both peripheral and internal renovations. These include the construction of a press conference hall capable of seating 200 individuals, as well as side areas for interpreters and technical staff. The exterior of the stadium is being fitted with ceramic panels that will illuminate in the future, featuring blue and red on the front and a brown hue that blends with the neighborhood on the sides, though they are not permitted to be lit every day. The three-tiered grandstand structure is also being equipped with shock-absorbing devices to enhance seismic safety in accordance with regulations.